Sep, 29, 2022

Meet the Developer Meeting

A Community Meeting co-led by VTA and Affirmed to introduce the project and the Design and Development Team to the community.

June 2023

Community Meeting #2

A presentation of the design of the project by the Development Team and the results of the Station Access study by the VTA.

September 2023

Planning Entitlement Submittal

November 2023

Open House (Community Meeting #3)

A presentation of the updated design of the project by the Development Team and VTA.

November 2024

Receive Entitlements

The City approves the project design

January 2026

Receive Permits

The project receives all the necessary approvals to start construction

February 2026

Construction Start

Project receives all the necessary permits and financing to start construction.

Sep, 01, 2027

Start the Lease-up Process

The team starts taking leasing applications

February 2028

Construction Completion

Project receives TCO and Move-ins start

June 2028

Lease-up Process Completed

100% of the units leases up